Wind and watertight for Christmas!

Yesterday we reached a major milestone with the delivery of the patio doors and main entrance door - the building was made wind and watertight and we now need a key to get in! This means that first-fixes and roughings can continue whatever the weather and the building is drying out nicely inside.


I've been working away from 'home' the last few days which has been frustrating, not least as there are many questions on detail items to deal with. I caught up after a half hour tour round this morning and it's clear that things are really moving on.

First fix electrics and plumbing are nearly all complete, with a few adjustments to make to the underfloor heating in the first floor bathroom and en-suite. Electrics are also nearly there with a few outstanding decisions to make on light switch locations and cooker load (ie. what cooker are we going to install!). The other first fixes remaining are the Heat Recovery Ventilation system ducting, TV/Satellite, phone, DAB (weak signal area for digital radio so need an aerial) and Cat 5 cabling.

Last but not least the slaters are making good progress and the stainless steel chimney for the wood stove looks superb, especially as the installation has been reinforced from the inside thus avoiding the need for external stays which might have spoilt the roofline.

Tags: windows

Comments: 0 (Add)

Check Availability

Loading