Future Plans
This week we've instructed the architect to commence work on plans for the former dairy. We're looking into the possibility of converting the building into holiday accommodation and prepared a brief to that end. We are very fortunate to live in a beautiful part of the world and the National Park designation has further enhanced this area's popularity for visitors. As you can see the slate roof is hanging together but there are some nice features to the building and we would like to bring it back into good use. The building is to the north of where our house will sit. The brief still adheres to our low energy principles but with an exisiting shell the approach will be different. At this stage we are looking at what sort of space we can create within the structure as it stands and exploring the planning situation.
Timber Frame Disappointment
Today the forklift was dropped off in order to be ready for Monday when the timber frame is due for delivery. Three year old son just said 'wow' and is very excited that more machinery is on site. Unfortunately a couple of phone calls and a visit from the builder brings news that certain elements of the kit are not ready - namely the steel portal frame and the first floor TGI joists. This means that work can start on erecting the timber frame next week but the extent will be limited because the steel portal is to be integrated within some of the prefabricated wall panels on site. This is disappointing for us but is outwith our control or influence so not worth stewing about. For the builder it is perhaps more frustrating, particularly as there has already been a break of three weeks of fairly good weather since significant work on site and as he has lined up scaffolding and crew to go full steam ahead on the frame.
Wall plates installed
On Tuesday of this week the builders spent the morning fitting the wall plates (also called 'sole plates'). In timber frame construction these set out the plan of the ground floor layout and form the interface between the walls (both external and internal) and the ground floor slab/foundations.
The wall plates comprise timber of the same width dimension of the wall panels they support (ie. 140mm and 89mm), and are simply cut to length and laid on a bed of mortar (and damp proof course at the outside walls).
Whilst an apparently straightforward process, locating the wall plates in the correct positions is critical to the ultimate accuracy of the frame installation.
As an aside, this process also introduced a simple but effective airtightness detail to the building, in that the overhanging damp proof membrane (from under the slab) is folded back over the slab at the edges for later trimming and connection to the vapour membrane to be installed on the inside of the wall panels. Whilst not an essential detail (and usually omitted), this ensures an airtight and flexible linear floor/wall joint that should last through the first few years of the building 'settling' and drying out, a process often responsible for significant degradation of airtighness as cracks open between differing materials (eg wood/mortar) and thus worsening energy efficiency. Polythene membrane, being a flexible material, withstands this movement.
As an aside, airtightness is a key component to low energy building design alongside insulation, the minimisation of thermal bridges, orientation and glazing. Coupled with this it is essential to have an effective ventilation system to ensure good air quality inside - more on this and other airtighness details as the house takes shape.
Four Months of Caravan Living
We've been living in the caravan for just over 4 months now, its hard to believe and generally has worked a lot better and been much easier than we expected (all those years of camping provides good training!). Yesterday was a horribly cold damp foggy day though and I felt chilled to the bone. By the evening I just couldn't get warm and the prospect of a warm bathroom in a real house would have been lovely. Its a better morning outside today but the water heater won't work and after attempts to remedy the problem we've called the engineer who is coming out this afternoon thankfully. If it doesn't work I'll be 'phoning a friend'.
We have two caravans both of which are on a concrete area, formerly one of the farm middens (for the English readers that's the place where all the cow muck is piled up!) Our main van has two wee bedrooms, a dining kitchen and a sitting/lounge area as well as a shower room with a sit-up bath tub which is great for the children. The cooking and heating (one gas fire) are by bottled LPG.
The second van is a bit smaller but has been kitted for the washing maching, tumble dryer and lots of clothes rails, our 'walk-in wardrobe'. Initially this van was used as our office and for our nephew who stayed here in the summer. One of the main problems with caravan living is the lack of space but we're lucky enough to have the second van and lots of outbuildings to overspill into.
We don't have a completion date as such but we can easily assume another 4 months to go, it is a nice thought that we're at our halfway point of temporary accommodation but we are now heading towards winter....!!!!
All quiet on site...
It's now two weeks since the floor slab was poured with most of the ground floor plumbing and underfloor heating pipes in-situ. The planning and preparation work appears to have paid off as overnight rain reveals little ponding of water indicating we have a flat and level slab within the specified tolerance. All services are also now in place within the slab, having been 'introduced' to the inside of the building via pipework and ducts, with just the soil pipes to be revealed by tapping away the few mm of concrete over their sealing caps. Little has happened since on site with the exception of the delivery of the timber frame sole plate material to be fitted in readiness for the main house frame, this being schduled for delivery w/c 29th October, although there has been much 'to-ing' and 'fro-ing' between frame supplier, builder, architect and client (us!) over minor changes to dimensions of components and materials. In the meantime, we've put some more effort into landscaping works and have started to plant up behind the drystone faced retaining wall, this being almost complete bar coping stones (proving quite hard to come by!).
Search and book
Tags
animals architectural design awards, cottages, sustainability bees caravan cottages Curlew Cottage days out design dogs eastcambusmoon electric vehicles foundation fruit and veg production furniture gold award great review green toursim hard landscaping heat pump heat recovery hens holiday accommodation insulation interiors lambing landscaping loch lomond low energy measures national park nature outings owls people photoshoot roof solar PV timber frame Training ventilation walks website windows
Blog archive
- June 2019 (1 entry)
- February 2019 (1 entry)
- December 2018 (1 entry)
- November 2018 (1 entry)
- April 2018 (1 entry)
- December 2017 (1 entry)
- October 2017 (2 entries)
- June 2017 (1 entry)
- April 2017 (2 entries)
- March 2017 (1 entry)
- February 2017 (1 entry)
- February 2016 (1 entry)
- June 2014 (1 entry)
- June 2013 (1 entry)
- April 2013 (1 entry)
- February 2013 (1 entry)
- May 2012 (2 entries)
- April 2012 (1 entry)
- March 2012 (2 entries)
- December 2011 (1 entry)
- August 2011 (2 entries)
- June 2011 (4 entries)
- May 2011 (4 entries)
- April 2011 (1 entry)
- December 2010 (4 entries)
- October 2010 (2 entries)
- August 2010 (2 entries)
- December 2009 (1 entry)
- November 2009 (2 entries)
- October 2009 (2 entries)
- September 2009 (3 entries)
- August 2009 (1 entry)
- July 2009 (2 entries)
- June 2009 (3 entries)
- May 2009 (7 entries)
- April 2009 (2 entries)
- March 2009 (2 entries)
- February 2009 (1 entry)
- January 2009 (4 entries)
- December 2008 (2 entries)
- November 2008 (1 entry)
- June 2008 (5 entries)
- May 2008 (4 entries)
- April 2008 (11 entries)
- March 2008 (14 entries)
- February 2008 (9 entries)
- January 2008 (12 entries)
- December 2007 (11 entries)
- November 2007 (11 entries)
- October 2007 (10 entries)
- September 2007 (6 entries)